SCOPE

This project will rehabilitate and replace watermain on Cosmopolitan Avenue and reconstruct the road. 

TIMELINE

Task
Completion Date
EngineeringMarch 2025
Bidding PhaseApril 2025
Construction Watermain LiningWeek of April 21, 2025
Consumers Energy Gas Main Replacement ProjectJuly 
Construction Watermain Replacement StartSeptember
Construction EndNovember
Project CloseoutSpring 2027


FUNDING

The funding for this project is paid for by the Water Department. Identified as a priority capital improvement project in the fiscal year 2024 budget, funding for this project is generated by the City's water utility rate payers. The total estimated costs of the project is $500,000. 

communications

The City strives to communicate with residents and property owners effectively. A summary of communication issued related to the Cosmopolitan Avenue construction project is listed below. To receive direct updates via email and text please create an account and sign up for Notify Me construction updates

DateCommunication
December 13, 2024Letter to Residents - Construction Introduction
January 1, 2025Notify Me - Construction Introduction
January 29, 2025Hand Delivered Construction Introduction to Residents
March 12, 2025Letter to Residents - Property Adjacent to Lining Project
March 17, 2025Notify Me - Lining Project Information
March 18, 2025
Letter to Residents -  Lining Project Schedule
April 23, 2025Notify Me - Cosmopolitan Watermain Lining Project
April 28, 2025Notify Me - Update on Watermain Lining - Extra Work Today
July 3, 2025Notify Me- Cosmopolitan Watermain and Construction Update
August 6, 2025Notify Me- Consumers Energy Gas Main Replacement Project
August 21, 2025Notify Me - Cosmopolitan Construction Update
August 21, 2025Letter to Residents - Cosmopolitan Construction Update
September 25, 2025Notify Me- Cosmopolitan Watermain Update
October 3, 2025Watermain Connection Update
October 6, 2025
Cosmopolitan Water Service Interruption and Road Closure
October 10, 2025Notify Me - Cosmopolitan Boil Water Advisory Lifted
October 22, 2025Notify Me- Cosmopolitan and North Drive Base Paving Update