S Kalamazoo Resurfacing Project

project map

Red Line on S Kalamazoo Ave

Sign up for Construction Notifications on S Kalamazoo Avenue Resurfacing Project

SCOPE

The City will be completing a mill and pave project on S Kalamazoo Avenue from Michigan Ave to Industrial Road.  Along with the road improvements, several sidewalk ramps will be repaired and brought to American with Disabilities Act (ADA) Standards.  The MDOT Office of Rail will be performing improvements to the railroad crossing during the street closure at the time identified below. 

timeline

Task
Completion Date
EngineeringApril 2023
BiddingMay 4, 2023
Construction - Mobilize*July 24, 202
S Kalamazoo Ave Closed - Industrial to SpruceJuly 24 - August 4, 2023
S Kalamazoo Ave - Industrial to Spruce PavingAugust 2, 2023
S Kalamazoo Ave Closed - Spruce to Michigan AveAugust 21, 2023
S Kalamazoo Ave  Paving - Spruce to Michigan AveAugust 29, 2023
S Kalamazoo Ave Open to Traffic - Spruce to Michigan AveSeptember 1, 2023
S Kalamazoo - Pavement MarkingsWeek of September 11, 2023
Project CloseoutTBD


*This project schedule  is dependent on the S Kalamazoo Ave  portion of the Industrial Road Watermain Project. 

funding

The City of Marshall was awarded a Michigan Department of Transportation (MDOT) Transportation Economic Development Fund (TEDF) Category F Grant for this project. The funding provides a grant of $285,000 towards the projects current construction estimate of $500,000. The remainder of the funding, approximately $215,000, will be support by the local street millage fund.