project map

scope
The Leggitt Road reconstruction project will include new watermain, sanitary sewer, stormwater management, and a complete new road surface.
timeline
Task | Completion Date |
Engineering | November 2022 |
Bidding | January 25, 2023 |
Mobilize | May 3, 2023 |
Construction - Mill Leggitt Road Asphalt Surface | COMPLETE |
Construction - S Kalamazoo Ave Intersection Closed | COMPLETE |
Construction - Watermain Installation | COMPLETE |
Construction - Sanitary Sewer Installation
| May 18, 2023 - June 9, 2023
|
Construction - S Kalamazoo Ave Intersection Closed | Estimated week of June 12, 2023 |
Construction - Stormwater Management Construction | May 22, 2023 - June 16, 2023 |
Construction - Street Surfacing | Estimated week of June 12, 2023 |
funding
This project is funded through several City funds including the Water Fund, Wastewater Fund, Local Streets Fund, and the Street Millage Fund. The total project is estimated at $715,000.